DAMAGES CLAIM AGAINST CITY PAVING SCHEME CONTRACTOR
Michael Fabricant has learned that damages are being claimed against the contractor responsible for the paving works around Lichfield Market Square. And the Council has said:
"We believe that a significant proportion of the delay can be attributed to the contractor not planning its work effectively, including at times having an inadequate number of skilled labourers on site to lay the paving and insufficient materials."
In a letter to Lichfield District Council at the beginning of September, Michael Fabricant asked:
"Have any additional costs, over and above the original contract cost, been incurred by the Council for the extended period of works?
"Has the contractor suffered any penalty charge for the extended period of works? Have any lessons been learned by the Council for the management of future projects? What has caused these excessive delays?"
In a detailed response to Michael Fabricant, the works implementation manager from the District Council wrote:
"The District Council is deeply disappointed that the project has taken longer than originally expected and I can reassure you that we are taking every step we can to ensure that the contractor finishes the work as soon as possible.
"I would like to make the following points:
1) The Contractor has indicated that the majority of the works will be finished by the end of September. However, as you know we have been given assurances of finish dates in the past and these have been missed. So, whilst we believe the date is achievable and likely, it is given with some degree of caution.
2) The Contract Administrator has issued Extensions of Time to the contract, currently totally 24.9 days, which will result in additional costs to the contract.
3) However, the District Council has notified the Contractor that we will be deducting Liquidated Damages for the non-completion of the scheme by the dates in the Contract. At present these are anticipated to total 51.1 days. It must be noted that both the Extension of Time and Liquidated Damages periods are subject to further contractual negotiation and may change.
4) The District Council put an enormous amount into the preparation and planning for this work, agreeing the timing, phasing and how we could keep the disruption to a minimum, with partners at the City and County Council, the Chamber of Trade and the Access Forum of the Disability Partnership.
We undertook a detailed and careful procurement process to appoint the contractor, based not only on price but also experience of similar projects and respective performance.
However, we could not plan for or foresee changes in personnel on site that duly occurred following the appointment of the contractor and we feel this is where a large number of problems have arisen.
When the project has finished the District Council will evaluate the management of the project and identify what lessons can be learnt.
5) There are several reasons for the delays to the project, and the views of the contractor and ourselves differ about a significant number of these.
We believe that a significant proportion of the delay can be attributed to the contractor not planning its work effectively, including at times having an inadequate number of skilled labourers on site to lay the paving and insufficient materials.
In terms of the approved extensions of time these relate to the need to re-lay parts of Breadmarket Street kerb line and paving as requested by Staffordshire County Council (12 days), additional works associated with the Bower weekend and the 2 military parades (2.4 days), the installation of the traffic management, additional investigations as to the construction of the carriageway and excavating around previously unidentified services.
Whilst we have maintained access to the city centre throughout the works, the extended length of the contract has, it is acknowledged, caused inconvenience to users of the city centre. We will continue to undertake the necessary steps to ensure the work is finished as soon as possible and that we can have the City Centre back to normal. We believe that when the works are finished they will enhance the character and appearance of the city centre making it a safer and more attractive place for visitors, residents and businesses.”
Michael Fabricant agrees.
“Unlike some recent construction close to the City Centre, I believe that the work in the Market Square is fully in keeping with the character of Lichfield and I welcome this much needed make-over. It will help attract additional tourism and boost the economy of the City. However, I am pleased the Council is taking a robust attitude regarding the costs of this project for they must never forget they are the guardians of council tax payers’ money.
“There are lessons to be learned as confirmed in the letter and in subsequent statements by councillors. Nevertheless, I recognise from my own experience as a chartered engineer that it is impossible to foresee every contingency on a major project such as this.
“I know that local traders and residents have been badly inconvenienced by all the disruption in the City Centre. I have received many complaints as well as observations about the degree of ‘work ethic’ amongst some of the builders on site. I have seen some of the builders sunbathing in the market square on the odd sunny day we had during the summer.
"What with barricades in the road and diverted traffic, there has been something of the Dunkirk Spirit amongst pedestrians in Lichfield this year. But in a few weeks from now, I hope most will say: ‘It was worth the wait’.”
Latest Press Releases
- AWM withdraws funding for Friarsgate Centre
- Fast trains on Sunday?
- Lichfield Trent Valley and Alrewas train stations
- Release of MP's expenses
- Fabricant welcomes Iraq memorial to Alrewas
- Alrewas gravel extraction walk
- Carers at breaking point
- Staffordshire is the new Surrey
- Michael Fabricant remembers Beijing 20 years ago
- Fabricant challenges housing targets